Worker scheduling problem

  • A grocery store has requirements for between 10 to 18 cashiers depending on the time of day.
  • Lunchtime, from noon to 2 p.m., and evening, from 5 p.m. to 6 p.m. are usually busiest.
  • The table below indicates the cashiers needed at various hours that the store is open:

Picture

  • The store now employs 27 full-time cashiers, but many people are on its roster of available part-time employees.
  • A part-time employee must put in exactly 4 hours per day but can start anytime between 9a.m. and 6 a.m.
  • Part-timers are a fairly inexpensive labour pool because no retirement or lunch/dinner benefits are provided to them. Full-timers, on the other hand, are divided into two groups, one group (i.e. 15 full-timers) works from 9 a.m. to 4 p.m., and the other group (i.e. 12 full-timers) works from 4p.m. to 10 p.m.
  • Both group of full-timers are allowed 1 hour for lunch/dinner.
  • For the group of full-timers who work from 9 a.m. to 4 p.m., half of the full-timers eat at 11 a.m., and the other half eat at 12noon).
  • For the group of full-timers who work from 4 p.m. to 10 p.m., half of the full-timers eat at 6 p.m.,and the other half eat at 7 p.m.).

  • The store limits part-time hours to a maximum of 50% of the day’s total requirement.
  • Part-timers earn RM 7.50 per hour, whereas full-timers earn RM 75 per day.

The management would like to set a schedule the number of full timers and part timers which can minimize the total man-power costs.

Solution

Let

$x_{1}$ = number of full-time cashiers work from 9a.m – 4p.m.

$x_{2}$ = number of full-time cashiers work from 4p.m – 10p.m.

$y_{1}$ = number of part time cashiers start work at 9a.m – 10a.m

$y_{2}$ = number of part time cashiers start work at 10a.m – 11a.m

$y_{3}$ = number of part time cashiers start work at 11a.m – 12noon

$y_{4}$ = number of part time cashiers start work at 12noon – 1p.m

$y_{5}$ = number of part time cashiers start work at 1p.m – 2p.m

$y_{6}$ = number of full-time cashiers work from 2p.m – 3p.m

$y_{7}$ = number of part time cashiers start work at 3p.m – 4p.m

$y_{8}$ = number of part time cashiers start work at 4p.m – 5p.m

$y_{9}$ = number of part time cashiers start work at 5p.m – 6p.m

$y_{10}$ = number of part time cashiers start work at 6p.m – 7p.m

LP formulation

$Min z = 75(x_{1}+x_{2}) + 30(y_{1}+y_{2}+y_{3}+y_{4}+y_{5}+y_{6}+y_{7}+y_{8}+y_{9}+y_{10})$

subject to

$x_{1}+y_{1} \ge 15$ $x_{1}+y_{1}+y_{2} \ge 10$ $1/2x_{1}+y_{1}+y_{2}+y_{3} \ge 12$ $1/2x_{1}+y_{1}+y_{2}+y_{3}+y_{4} \ge 18$ $x_{1}+y_{2}+y_{3}+y_{4}+y_{5} \ge 18$ $x_{1}+y_{3}+y_{4}+y_{5}+y_{6} \ge 16$ $x_{1}+y_{4}+y_{5}+y_{6}+y_{7} \ge 12$ $x_{2}+y_{5}+y_{6}+y_{7}+y_{8} \ge 15$ $x_{2}+y_{6}+y_{7}+y_{8}+y_{9} \ge 18$ $1/2x_{2}+y_{7}+y_{8}+y_{9}+y_{10} \ge 16$ $1/2x_{2}+y_{8}+y_{9}+y_{10} \ge 10$ $x_{2}+y_{9}+y_{10} \ge 12$ $x_{2}+y_{10} \ge 12$ $4(y_{1}+y_{2}+y_{3}+y_{4}+y_{5}+y_{6}+y_{7}+y_{8}+y_{9}+y_{10}) \le 92$ $x_{1} \le 15$ $x_{2} \le 12$

$x_{1},x_{2},y_{1},y_{2},y_{3},y_{4},y_{5},y_{6},y_{7},y_{8},y_{9},y_{10} \ge 0

Picture

For the result,they need 12 full-time employee work from 9a.m.-4p.m.

10 full-time employee work from 4p.m to 10p.m.

20 part time cashier should hired

This minimize the total number of full-time cashiers from 27 to 22.

PeriodFull timePart time
9a.m - 10a.m123
10a.m - 11a.m123
11a.m - 12noon612
12noon - 1p.m612
1p.m - 2p.m129
2p.m - 3p.m129
3p.m - 4p.m120
4p.m - 5p.m109
5p.m - 6p.m109
6p.m - 7p.m511
7p.m - 8p.m511
8p.m - 9p.m102
9p.m - 10p.m102